SUSPENSION OF COUNCIL RULE VIII FOR THE FOLLOWING ITEMS:
(2/3 Vote Required)
A motion was made by Richmond, seconded by Sleznikow to SUSPEND
Council Rule VIII for items 22-0150, 22-0151, 22-0187, and 22-0195; the motion
carried unanimously.
REPORT OF BIDS/QUOTES RECOMMENDED TO BE ADOPTED
Report of Bids & Resolution awarding contract to Poellinger Electric, Inc. for
the 10th & Cass Lighting Addition Project in the amount of $55,856.44.
Withdrawn - duplicate of file 22-0069.
Report of Bids & Resolution awarding contract to Americon for the Weigent
Park Shelter Project Re-Bid in the amount of $576,000.00.
2022-02-004
A motion was made by Mindel, seconded by Kiel, that the Resolution be
ADOPTED. The motion carried by the following vote:
13 -
Yes:
Richmond, Neumeister, Janssen, Sleznikow, Weaver, Kahlow, Kiel, Mindel,
Woodard, Schwarz, Trost, Happel, Neumann
Report of Bids & Resolution awarding contract to Poellinger Electric, Inc. for
the 10th & Cass Lighting Addition Project in the amount of $55,856.44.
2022-02-005
A motion was made by Kahlow, seconded by Sleznikow, that the Resolution be
ADOPTED. The motion carried by the following vote:
13 -
Yes:
Richmond, Neumeister, Janssen, Sleznikow, Weaver, Kahlow, Kiel, Mindel,
Woodard, Schwarz, Trost, Happel, Neumann
Report of Bids & Resolution awarding contract to Poellinger Electric, Inc. for
the 2022 Pedestrian Lighting (Gillette St & Onalaska Ave) Project in the
amount of $547,650.68.
2022-02-006
A motion was made by Richmond, seconded by Neumeister, that the
Resolution be ADOPTED. The motion carried by the following vote:
13 -
Yes:
Richmond, Neumeister, Janssen, Sleznikow, Weaver, Kahlow, Kiel, Mindel,
Woodard, Schwarz, Trost, Happel, Neumann
Report of Bids & Resolution awarding contract to Fowler & Hammer, Inc. for
the Green Bay Sidewalk and Curb Ramp Replacement Project in the amount
of $48,085.00.
2022-02-007
A motion was made by Kahlow, seconded by Schwarz, that the Resolution be
ADOPTED. The motion carried by the following vote: