File #: 15-0671    Version: 2 Name: Poage Park Redevelopment Plan (TIF 14) (HUD)
Type: Report of Bids Status: Adopted
File created: 6/10/2015 In control: Common Council
On agenda: 7/9/2015 Final action: 7/9/2015
Title: Report of Bids & Resolution Awarding Contract to Borton Construction Company in the amount of $977,700.00 base bid with Alternates A,C,D for the Poage Park (HUD) Project.
Attachments: 1. Resolution, 2. Engineer Letter

Title

Report of Bids & Resolution Awarding Contract to Borton Construction Company in the amount of $977,700.00 base bid with Alternates A,C,D for the Poage Park (HUD) Project.

Fiscal Note

22568215-578010-02321 (2013 CDBG)                                                                                                                              $92,737.89

22558215-578010-02321 (2012 CDBG)                                                                                                                              $71,597.51

TID #14 Gundersen Lutheran Share (Developer’s Agreement)(2014 CIP #240)                     $150,000.00

TID #14 City Share (Gundersen Developer’s Agreement)(2014 CIP #240)                                          $150,000.00

2014-A Promissory Note (Parks) (Poage Park Development)                                                               $513,364.60