File #: 21-0014    Version: 2 Name: ROB Moorings Drive Storm & Rip Rap Project
Type: Resolution Status: Adopted
File created: 1/6/2021 In control: Common Council
On agenda: 2/11/2021 Final action: 2/11/2021
Title: Report of Bids & Resolution awarding contract to Winona Mechanical, Inc. in the amount of $57,279.25 for the Moorings Drive Storm & Rip Rap project.
Attachments: 1. Resolution, 2. Engineer Letter

Title

Report of Bids & Resolution awarding contract to Winona Mechanical, Inc. in the amount of $57,279.25 for the Moorings Drive Storm & Rip Rap project.

Fiscal Note

2020 CIP #513 Curb & Gutter                                                               $28,000.00

2020 CIP #513 Storm Water Utility Funds                     $7,000.00

2020 CIP #514 Rip Rap                                                               $22,279.25