File #: 14-0211    Version: 2 Name: Resolution awarding contract for 2014 Sidewalk Curb Ramp Replacement Project
Type: Report of Bids Status: Adopted
File created: 2/18/2014 In control: Common Council
On agenda: 3/13/2014 Final action: 3/13/2014
Title: Report of Bids and Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $212,702.00 for the 2014 Sidewalk & Curb Ramp Replacement Project.
Attachments: 1. Engineer Bid Letter, 2. Resolution
Title
Report of Bids and Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $212,702.00 for the 2014 Sidewalk & Curb Ramp Replacement Project.
Fiscal Note
Revolving Assessment Account                  $147,702.00
2014 Water Utility Funds                        $20,000.00
2014 Street Department Operating Budget            $5,000.00
2009-A Promissory Note (Street)(2014 CIP#76)      $12,000.00
2007-A Corporate Purpose (Street)(2014 CIP#76)      $28,000.00