File #: 25-0326    Version: 1 Name: Report of Bids and Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $148,662.00 for the 2025 Citywide Miscellaneous Curb Ramp & Sidewalk Replacement project.
Type: Resolution Status: Adopted
File created: 3/12/2025 In control: Common Council
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Report of Bids and Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $148,662.00 for the 2025 Citywide Miscellaneous Curb Ramp & Sidewalk Replacement project.
Attachments: 1. Resolution, 2. Engineer Letter

Title

Report of Bids and Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $148,662.00 for the 2025 Citywide Miscellaneous Curb Ramp & Sidewalk Replacement project.

 

Fiscal Note

CIP 648 New Debt Issue                                          $99,667.00

Resolution 25-0477                                                               $48,995.00

 

CIP 648 New Debt Issue (Contingency)                     $333.00

Resolution 25-0477 (Contingency)                                          $11,005.00