File #: 17-0053    Version: 1 Name: 2017 Curb Ramp-Corner Replacement project
Type: Report of Bids Status: Adopted
File created: 1/10/2017 In control: Common Council
On agenda: 2/9/2017 Final action: 2/9/2017
Title: Report of Bids & Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $52,995.00 for the 2017 Curb Ramp-Corner Replacement project.
Attachments: 1. Resolution, 2. Engineer Letter

Title

Report of Bids & Resolution awarding contract to Fowler & Hammer, Inc. in the amount of $52,995.00 for the 2017 Curb Ramp-Corner Replacement project.

Fiscal Note

Reserve Fund                                                               $40,000.00

Storm Water Utility Funds                     $12,995.00