File #: 18-1253    Version: 1 Name: Proposed change order, and contractor dispute, on the VIP Trail Extension project with Pember Companies
Type: General Item Status: Approved
File created: 9/6/2018 In control: Board of Public Works
On agenda: 9/17/2018 Final action: 9/17/2018
Title: Change order, and contractor dispute, on the VIP Trail Extension project with Pember Companies. (Note: The Committee and/or Council may convene in closed session pursuant to Wis. Stat. 19.85(1)(e) to formulate & update negotiation strategies and parameters. Following such closed session, the Committees and/or Council may reconvene in open session.)
Attachments: 1. Change Order - approved, 2. Proposed Change Order #1

Title

Change order, and contractor dispute, on the VIP Trail Extension project with Pember Companies.  (Note:  The Committee and/or Council may convene in closed session pursuant to Wis. Stat. 19.85(1)(e) to formulate & update negotiation strategies and parameters.  Following such closed session, the Committees and/or Council may reconvene in open session.)